Which of the following consists of different products that share similar characteristics,components or manufacturing processes?


A) Resource tree
B) Product family
C) Dependant allocation
D) Implosion factor

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

Which of the following seeks to develop short range plans seeking to effectively and efficiently manage components and/or subassemblies over time period of few days to a few weeks?


A) RRP
B) MPS
C) RCCP
D) MRP

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

System nervousness is when even small changes to upper-level production plans cause major changes in lower-level production plans.

A) True
B) False

Correct Answer

verifed

verified

In a bill of materials,items at which level are independent demand items?


A) Level 0
B) Level 1
C) Level 2
D) Level 3

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

Which of the following could be considered a master production schedule for a service firm?


A) The reservation book utilized by a restaurant
B) The employee shift schedule utilized by an auto shop
C) A hospital patient's personal information fill
D) The recipe book utilized by a chef at a restaurant

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

While ERP is a relatively new technology,it has grown rapidly since the early 1990s.Which of the following is the reason that has contributed to its rapid growth?


A) The year 2000 millennium bug
B) The trend for companies to eliminate their supply chain partners
C) The increased use of email during the 1990's
D) All of these

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

The acronym ERP is short for:


A) Enterprise Resource Planning
B) Electronic Resource Provider
C) Executive Resource Plan
D) Electronic Requirements Provider

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Which of the following is an engineering document that shows an inclusive listing of all the component parts and assemblies making up the final product?


A) Master Production Schedule
B) Bill of Materials
C) Distribution Requirement Plan
D) Resource Requirement Plan

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

Which number should be placed in the spot presently filled with the X? Which number should be placed in the spot presently filled with the X?   A)  10 B)  15 C)  30 D)  60


A) 10
B) 15
C) 30
D) 60

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

To check the feasibility of the Master Production Schedule,one would look to:


A) Rough-Cut Capacity Plan
B) Material Requirement Plan
C) Capacity Requirement Plan
D) Distribution Requirement Plan

E) A) and D)
F) A) and B)

Correct Answer

verifed

verified

MRP is the production planning system intended to develop long-range plans (more than a year away)concerning product families manufactured by the organization.

A) True
B) False

Correct Answer

verifed

verified

When a single company that is implementing an ERP system chooses to use one company to provide an operations module,another to provide the sales and marketing application,and yet another company to provide the finance and accounting module,that single company has chosen to utilize the best-of-breed solution.

A) True
B) False

Correct Answer

verifed

verified

Which of the following basic production strategies used for addressing the aggregate planning problem would work best with make-to-order manufacturing firms?


A) Capacity Production Strategy
B) Chase Production Strategy
C) Level Production Strategy
D) Backlog Production Strategy

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

A Mixed Production Strategy uses a blend of chase and level strategies by striving to maintain a stable core workforce while using other means like temporary workers to manage short-term high demand.

A) True
B) False

Correct Answer

verifed

verified

Complete the Projected on hand inventory Row Complete the Projected on hand inventory Row

Correct Answer

verifed

verified

Key requirements to a successful ERP implementation include adequate computer support,accurate system inputs,and flexible business processes that can conform to the approaches used in the ERP software logic.

A) True
B) False

Correct Answer

verifed

verified

An MRP system has a subassembly with a lot size of 100 units.In terms of filling future requirements,this would mean that planned order releases for the subassembly would always have to be exactly 100 units.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is considered an advantage/benefit of utilizing an ERP system?


A) Fairly inexpensive to purchase and implement
B) Enables the company to utilize a single centralized database system, thus eliminating duplicate data entry.
C) Flexible enough that it allows different companies with different business models to mold the new ERP system to fit the company's business model
D) All of these

E) None of the above
F) All of the above

Correct Answer

verifed

verified

Which number should be placed in the spot presently filled with the X? Which number should be placed in the spot presently filled with the X?   A)  20 B)  5 C)  45 D)  35


A) 20
B) 5
C) 45
D) 35

E) C) and D)
F) A) and D)

Correct Answer

verifed

verified

What does that mean if your organization has chosen to adopt a best-of-breed solution?

Correct Answer

verifed

verified

ERP systems utilize numerous application...