NPV analysis is a method for making equal comparisons between cash flows for multi-year projects.

A) True
B) False

Correct Answer

verifed

verified

A(n) _____ is a formal group of people responsible for approving or rejecting changes to a project.

Correct Answer

verifed

verified

change control board...

View Answer

The _____ stage of information technology planning outlines business processes that are central to achieving strategic goals and helps determine which ones could most benefit from information technology.


A) project planning
B) business area analysis  
C) resource allocation
D) information technology strategy planning

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The _____ section of the project plan should describe the major project functions and activities and identify those individuals who are in charge of them.


A) organizational charts  
B) other organizational or process-related information  
C) project responsibilities  
D) management objectives

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

An IT company revises its process parameters in response to complaints from vendors that products were not ready on time. This would be an example of _____.


A) cost forecasting
B) a preventive action  
C) defect repairs
D) a corrective action

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

_____ refer to chances to improve the organization.

Correct Answer

verifed

verified

_____ factors include relevant government or industry standards, the organization's infrastructure, and marketplace conditions.

Correct Answer

verifed

verified

Enterprise...

View Answer

It is necessary that IT project managers have prior technical experience in creating and managing IT products.

A) True
B) False

Correct Answer

verifed

verified

A SWOT analysis, being a linear process, cannot be performed using the nonlinear mind mapping technique.

A) True
B) False

Correct Answer

verifed

verified

_____ are new requirements imposed by management, government, or some external influence.

Correct Answer

verifed

verified

Many projects fail because of unclear requirements and expectations, so starting with a payback analysis makes a lot of sense.

A) True
B) False

Correct Answer

verifed

verified

The business case includes information on _____.


A) the business need for the project  
B) relevant government or industry standards  
C) the project objective, high-level requirements, and time and cost goals  
D) policies, procedures, guidelines, and systems that influence a project's success

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

An organization's information technology project selection process should guide the strategic plan.

A) True
B) False

Correct Answer

verifed

verified

_____ involves coordinating all planning efforts to create a consistent, coherent document.


A) Developing the project charter  
B) Developing the preliminary project scope statement  
C) Developing the project management plan  
D) Developing the organizational process assets updates

E) C) and D)
F) A) and D)

Correct Answer

verifed

verified

A(n) _____ is a methodology that converts value drivers, such as customer service, innovation, operational efficiency, and financial performance, to a series of defined metrics.

Correct Answer

verifed

verified

_____ project work includes collecting, measuring, and disseminating performance information.

Correct Answer

verifed

verified

Organizational process asset updates are an important output of the closing process of a project.

A) True
B) False

Correct Answer

verifed

verified

Information systems can help an organization support a strategy of being a low-cost producer.

A) True
B) False

Correct Answer

verifed

verified

In a weighted scoring model, the sum of the weights of all the criteria must total _____ percent.


A) 10
B) 50  
C) 100
D) 150

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

The number of interfaces in a single project is limited, and does not depend on the number of people involved in the project.

A) True
B) False

Correct Answer

verifed

verified