The first step in creating a work breakdown structure (WBS) is to _____.


A) mark all recognizable events
B) determine time requirements
C) listall tasks
D) estimate task completion time and cost

E) None of the above
F) All of the above

Correct Answer

verifed

verified

The _____ is the most pessimistic outcome of a task.


A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) dominant-case estimate (D)

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

The prior experience method to make time and cost estimates works best for large projects.

A) True
B) False

Correct Answer

verifed

verified

In most systems analysis tasks, time and people are interchangeable.

A) True
B) False

Correct Answer

verifed

verified

System developers can initiate a formal project as early as the preliminary investigation stage, or later on, as analysis, design, and implementation activities occur.

A) True
B) False

Correct Answer

verifed

verified

Project managers always must be aware of the _____, so they can monitor the vital tasks and keep a project on track.


A) absolute path
B) relative path
C) critical path
D) dynamic path

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

A(n) _____ is a series of tasks that, if delayed, would affect the completion date of the overall project.


A) critical path
B) dynamic path
C) absolute path
D) relative path

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

A

Program Evaluation Review Technique (PERT) is a _____ technique because it analyzes a large, complex project as a series of individual tasks.


A) top-down
B) bottom-up
C) three-point estimate
D) six-point estimate

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

A _____ negotiates with users who might have conflicting requirements or want changes that would require additional time or expense.


A) project manager
B) project reporter
C) software tester
D) software developer

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

A continuous risk-tracking process can _____.


A) notice changes in existing risks
B) revert reported risks
C) prevent human resource turnover issues
D) prevent new issues

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

A

A _____ is a series of events and activities with no slack time.


A) risk path
B) foundation path
C) baseline path
D) critical path

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

A(n) _____ is a recognizable reference point that can be used to monitor progress.


A) event
B) notification
C) alert
D) task

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

_____, a human resource issue, is a possible cause of cost overruns in an organization.


A) Inadequate training
B) Inaccurate demand forecast
C) Poor monitoring of progress
D) Unrealistic estimates

E) A) and D)
F) B) and D)

Correct Answer

verifed

verified

Matching Identify the letters of the choices that best match the phrases or definitions. -A condition, restriction, or requirement that a system must satisfy


A) Project management
B) Project coordinator
C) Project leader
D) Milestone
E) Constraint
F) Weight
G) Program Evaluation Review Technique (PERT)
H) dependent
I) Concurrent tasks
J) Predecessortasks

K) A) and F)
L) C) and D)

Correct Answer

verifed

verified

If any task along a critical path falls behind schedule, the entire project will be delayed.

A) True
B) False

Correct Answer

verifed

verified

Matching Identify the letters of the choices that best match the phrases or definitions. -Handles the administrative responsibilities for a development team


A) Project management
B) Project coordinator
C) Project leader
D) Milestone
E) Constraint
F) Weight
G) Program Evaluation Review Technique (PERT)
H) dependent
I) Concurrent tasks
J) Predecessortasks

K) G) and J)
L) E) and J)

Correct Answer

verifed

verified

Matching Identify the letters of the choices that best match the phrases or definitions. -Usually a senior systems analyst or an IT department manager, if the project is large


A) Project management
B) Project coordinator
C) Project leader
D) Milestone
E) Constraint
F) Weight
G) Program Evaluation Review Technique (PERT)
H) dependent
I) Concurrent tasks
J) Predecessortasks

K) A) and H)
L) All of the above

Correct Answer

verifed

verified

Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers, as a form of peer review, in structured walk-throughs.

A) True
B) False

Correct Answer

verifed

verified

Project reporting, an activity of a project manager, _____.


A) involves the creation of a specific timetable, usually in the form of charts that show tasks, task dependencies, and critical tasks that might delay a project
B) includes informing management, users, and the project team about the progress of a project
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

A(n) _____ is an event that could affect a project negatively.


A) issue
B) webinar
C) uncertainty
D) risk

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

D