Filters
Question type

Study Flashcards

Describe the general steps recommended by the authors for designing and using the WBS.

Correct Answer

verifed

verified

Step 1: Using information from the actio...

View Answer

Once the project charter is completed and the project approved,a more detailed project plan can be developed.Which of the following issues is not addressed in the detailed project plan?


A) Developing a plan for managing the human resources assigned to the project
B) Developing a plan for continuously monitoring and improving project work processes
C) Developing the Work Breakdown Structure
D) Developing a list of skilled workers to hire

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

There are 12 Agile Principles to guide the implementation of Agile Project Management (APM) .Which of the following is not one of those 12 principles?


A) Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.
B) Define all of the requirements up-front so that changes are minimized later in the process.
C) Deliver working software frequently,from a couple of weeks to a couple of months.
D) Business people and developers must work together daily throughout the project.

E) A) and D)
F) B) and D)

Correct Answer

verifed

verified

Having key stakeholders involved early in the project tends to


A) increase communication errors
B) increase project risk
C) create buy-in
D) create more problems than it is worth

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

RACI stands for


A) responsive,accountable,consult,inform
B) responsible,accountable,consult,inform
C) responsive,accountable,consult,integrate
D) responsible,admissible,consult,integrate

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

B

A useful tool for facilitating the management of changes to a project's scope is the


A) requirements traceability matrix
B) WBS
C) project charter
D) mind map

E) All of the above
F) None of the above

Correct Answer

verifed

verified

The project plan must be designed in such a way that the project outcome meets __________.


A) the objectives of the parent organization
B) unauthorized requests for change in the project outcome
C) the requirements associated with scope creep
D) only the expressed warranties identified in the contract

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

In an agile project,teams are given several requirements but only deal with one at a time,with each iteration being referred to as a __________.


A) sprint
B) deliverable
C) WBS
D) control

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

A __________ must be submitted for any changes requested after the project plan has been approved.


A) change permission form
B) change form
C) change requirement application
D) change order

E) A) and D)
F) A) and B)

Correct Answer

verifed

verified

D

This element of the project plan,at a high-level,this covers potential problems as well as potential lucky breaks that could affect the project.


A) Schedule
B) Resources
C) Risk management plans
D) Evaluation methods

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

Which of the following is not another name for stage gates?


A) Phase gates
B) Quality gates
C) Transition points
D) Toll gates

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

This project plan element lists all milestone events.It identifies the estimated time for each task and is used to construct the master project schedule.


A) Budget
B) Schedule
C) Personnel plan
D) Evaluation methods

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

Identify four important outcomes associated with the project launch meeting.

Correct Answer

verifed

verified

The technical scope should be establishe...

View Answer

__________is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization.Typically,the upper level sets the objectives for the next lower level.


A) Strategic planning
B) Organizational planning
C) Hierarchical planning
D) Agile planning

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Agile IT project teams are typically __________ and located at __________.


A) large,a single site
B) small,multiple sites
C) large,multiple sites
D) small,a single site

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

D

There are 12 Agile Principles to guide the implementation of Agile Project Management (APM) .Which of the following is not one of those 12 principles?


A) Continuous attention to technical excellence and good design enhances agility.
B) Efficiency-the art of maximizing the amount of work that is accomplished in a given period of time-is essential.
C) The best architectures,requirements,and designs emerge from self-organizing teams.
D) At regular intervals,the team reflects on how to become more effective,then tunes and adjusts its behavior accordingly.

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

When using a WBS,all of the work should roll up to the next level such that no extra work is required.This is referred to as the ____________________.


A) Development rule
B) All-inclusive rule
C) 100% rule
D) WBS rule

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

This element of the project plan contains a brief description of the procedure to be followed in monitoring,collecting,storing,and evaluating the history of the project.


A) Schedule
B) Resources
C) Personnel
D) Evaluation methods

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

When the project is to deliver a product / service to an outside client,the project's scope cannot be altered without whose permission?


A) Senior management
B) Project management
C) Project Engineer
D) Client

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

The __________ chart is a tree diagram used to represent a hierarchical plan.


A) PERT
B) GANTT
C) PMBOK
D) Gozinto

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

Showing 1 - 20 of 44

Related Exams

Show Answer