Which of the following is/are included in a Project Cost-Duration Graph?


A) Total indirect cost
B) Total direct cost
C) Total project cost
D) Both A and B are correct
E) A, B, and C are all correct

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Collecting crash times for a moderate-size project is relatively easy.

A) True
B) False

Correct Answer

verifed

verified

The total cost for each possible duration of a project is the sum of labor, materials, and equipment.

A) True
B) False

Correct Answer

verifed

verified

A network is considered to be ________ if it has a predominate critical path with no other path close in terms of slack.

Correct Answer

verifed

verified

insensitive
Explanation: There is a posi...

View Answer

The most common response for meeting unattainable deadlines is to


A) Reduce or scale back the scope of the project.
B) Decrease the critical paths
C) Crash all elements of the project
D) Change the time to market statement
E) B, and C are correct

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

An activity's ________ is calculated by dividing the rise by the run.

Correct Answer

verifed

verified

slope
Expl...

View Answer

According to ________, adding more manpower to a late software project makes it later.

Correct Answer

verifed

verified

Brooks' law
Explanat...

View Answer

Incentive contracts can make reduction of project time rewarding-usually for both the project contractor and owner.

A) True
B) False

Correct Answer

verifed

verified

A common method for shortening the project time is to:


A) Adding resources
B) Schedule overtime
C) Subcontract an activity
D) Both A and B are correct
E) A, B, and C are all correct

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

The sum of the costs of all the work packages represents the total direct costs for the project.

A) True
B) False

Correct Answer

verifed

verified

Cost slope can be determined by dividing the


A) Run by the rise
B) Rise by the run
C) Crash cost by the normal cost
D) Normal cost by the crash cost
E) Both B and C are correct

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

Shortening an activity's duration is termed crashing.

A) True
B) False

Correct Answer

verifed

verified

Identify and briefly describe five reasons for attempting to reduce the duration of a project.

Correct Answer

verifed

verified

1.imposed durations made by top manageme...

View Answer

The higher the slope of an activity the greater the cost to reduce its duration.

A) True
B) False

Correct Answer

verifed

verified

Crashing a project should occur:


A) As early as possible
B) As late as possible
C) Midway through the project
D) Both A and C are correct
E) Cannot be determined with the information given

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

Given an equal level of risk and the need to reduce overall project duration, why would you not select the activity with the lowest slope in the entire project network to crash first?

Correct Answer

verifed

verified

If it is not on the ...

View Answer

Draw a typical Project Cost-Duration Graph and label the key elements.

Correct Answer

verifed

verified

See Figure...

View Answer

The easiest way to add more labor to a project is not to add more people, but to add ___________.

Correct Answer

verifed

verified

overtime
Explanation: The easi...

View Answer

Managers have several effective methods for crashing specific project activities when resources are not constrained.

A) True
B) False

Correct Answer

verifed

verified

Identify options for accelerating a project schedule when resources are constrained or the budget is severely constrained.

Correct Answer

verifed

verified

1.fast-tracking, 2.critical ch...