One criterion for developing effective schedules is minimizing completion time.

A) True
B) False

Correct Answer

verifed

verified

An approach to sequencing that can handle the situation where jobs must pass through two or more work centers in a fixed sequence is ________.

Correct Answer

verifed

verified

What is a method of input-output control that uses a system of cards to limit the amount of work at a work center and also to control lead time and monitor backlog?


A) the assignment method
B) backward scheduling
C) forward scheduling
D) ConWIP cards
E) level material use

F) C) and E)
G) D) and E)

Correct Answer

verifed

verified

Identify some scheduling optimization systems that are used at retail stores.Describe what these systems do.

Correct Answer

verifed

verified

Workbrain,Cybershift,and Krono...

View Answer

Eight jobs have been sequenced at a single work center.Total processing time for the eight jobs is 34 hours,and total flow time for the sequence is 85 hours.For this schedule,utilization is ________ and the average number of jobs in the system is ________.


A) 100 percent;10.625
B) low;.0941
C) 0.400 or 40 percent;2.5
D) 0.235 or 23.5 percent;4.25
E) maximized;minimized

F) D) and E)
G) C) and E)

Correct Answer

verifed

verified

________ scheduling begins with the due date and schedules the final operation first and the other job steps in reverse order.

Correct Answer

verifed

verified

The emergency room at a hospital estimates the following requirements for registered nurses (RNs)for the late night shift each week.Nurses work four consecutive days,then have off three days. The emergency room at a hospital estimates the following requirements for registered nurses (RNs)for the late night shift each week.Nurses work four consecutive days,then have off three days.    Perform cyclical scheduling on the data.(Note that you must identify three-day patterns of minimum requirements).How many RNs are required? How much extra capacity is required? Perform cyclical scheduling on the data.(Note that you must identify three-day patterns of minimum requirements).How many RNs are required? How much extra capacity is required?

Correct Answer

verifed

verified

blured image Days off are shaded.Seven full-time RNs...

View Answer

What is the assignment method?

Correct Answer

verifed

verified

The assignment method is a spe...

View Answer

What are some limitations of rule-based scheduling systems?

Correct Answer

verifed

verified

Three limitations are (1)Rules need to b...

View Answer

Bob Dresser operates a major appliance warranty service center.His operation has two check stations that are required at the end of every repair task performed by his appliance repair staff.These are the Functionality Review (FR)and the Overall Scan (OS).The FR must be performed successfully before the OS is begun.On Friday morning,six repair jobs are completed,awaiting these two inspection activities.Processing times are given in minutes. Bob Dresser operates a major appliance warranty service center.His operation has two check stations that are required at the end of every repair task performed by his appliance repair staff.These are the Functionality Review (FR)and the Overall Scan (OS).The FR must be performed successfully before the OS is begun.On Friday morning,six repair jobs are completed,awaiting these two inspection activities.Processing times are given in minutes.    a.What is the optimal sequence of jobs for the objective of minimizing the total flow time? b.Show your work,and document the sequence. c.Chart the solution to this problem. d.What jobs are being processed at time period 90? e.What is the total flow time of this problem?   a.What is the optimal sequence of jobs for the objective of minimizing the total flow time? b.Show your work,and document the sequence. c.Chart the solution to this problem. d.What jobs are being processed at time period 90? e.What is the total flow time of this problem? Bob Dresser operates a major appliance warranty service center.His operation has two check stations that are required at the end of every repair task performed by his appliance repair staff.These are the Functionality Review (FR)and the Overall Scan (OS).The FR must be performed successfully before the OS is begun.On Friday morning,six repair jobs are completed,awaiting these two inspection activities.Processing times are given in minutes.    a.What is the optimal sequence of jobs for the objective of minimizing the total flow time? b.Show your work,and document the sequence. c.Chart the solution to this problem. d.What jobs are being processed at time period 90? e.What is the total flow time of this problem?

Correct Answer

verifed

verified

(a)The optimal sequence is F-D-B-A-C-E.(...

View Answer

There are 5 jobs (A,B,C,D, E)that need to be completed in a work center.The due dates are the 10th,13th,9th,20th,and 15th respectively with process times of 7,12,7,20,and 10 respectively as well.If today is the 1st of the month calculate the critical ratio for each and use this value to sequence the jobs in the order they should be started.

Correct Answer

verifed

verified

A = (10 - 1)/7 = 1.29
B = (13 ...

View Answer

Which of the following is an advantage of the FCFS dispatching rule when used in services?


A) FCFS maximizes utilization.
B) FCFS minimizes the average number of jobs in the system.
C) FCFS minimizes the average lateness of all jobs.
D) FCFS maximizes the number of jobs completed on time.
E) FCFS seems fair to customers.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

At Morgan's Transformer Rebuilding,five jobs are ready now for dispatching to a machine center.The processing times and due dates for the jobs are given below.Use earliest due date to sequence the jobs,and calculate the average completion time,the average job lateness,and the average number of jobs in the machine center. At Morgan's Transformer Rebuilding,five jobs are ready now for dispatching to a machine center.The processing times and due dates for the jobs are given below.Use earliest due date to sequence the jobs,and calculate the average completion time,the average job lateness,and the average number of jobs in the machine center.

Correct Answer

verifed

verified

The EDD sequence is E-C-B-A-D....

View Answer

What is the priority rule that sequences jobs using the smallest ratio of due date from today to processing time?


A) critical ratio
B) earliest due date
C) first come,first served
D) longest processing time
E) shortest processing time

F) B) and D)
G) All of the above

Correct Answer

verifed

verified

What is the objective of scheduling?


A) maximize quality
B) minimize cost
C) minimize response time
D) prioritize and allocate demand to available facilities
E) minimize lead time

F) A) and C)
G) All of the above

Correct Answer

verifed

verified

In the sequence of decisions that affect scheduling,________ is (are)the immediate follower(s)of the master schedule (or master production schedule).

Correct Answer

verifed

verified

short-term...

View Answer

The assignment method is:


A) a method to highlight overloads in a given work center.
B) a computerized method of determining appropriate tasks for an operation.
C) a form of linear programming for optimally assigning tasks or jobs to resources.
D) the same thing as the Gantt schedule chart.
E) a method for achieving a balance between forward and backward scheduling.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Scheduling optimization systems used in retail stores typically track customer traffic in 4-hour time increments.

A) True
B) False

Correct Answer

verifed

verified

Given the table below,find the sequence for the following priority rules: (a)SPT (b)EDD (c)LPT Given the table below,find the sequence for the following priority rules: (a)SPT (b)EDD (c)LPT

Correct Answer

verifed

verified

(a)BACD
(b...

View Answer

Because of the significance of labor in the scheduling of services,behavioral and social issues,wage and hour laws,and union contracts all complicate the scheduling process.

A) True
B) False

Correct Answer

verifed

verified